Once again, hunting season is upon us. The area of the Trace owned by the Corps of Engineers is open for hunting through the end of deer season, in early January. Trails traversing Corps-owned property (all areas in yellow on Trail System map) are closed to other users until 10:00 am each morning. AS ALWAYS, wear bright colors when enjoying the Wilderness. Be safe!
Activity History
2024
Work Day - 04/27/2024
-
- White - Church to Meadow - completed blazing
-
- White - church kiosk toward Boling - completed re-blazing about a half mile of trail
-
- White - removed large tree blocking the trail close to the meadow
-
- White - repairs to bridge close to church
-
- White - cleaned up overgrown area around church kiosk
-
- Yellow - re-blazed entire trail
-
- Orange - removed large tree blocking the trail close to Shoal Creek road
-
- Orange - removed medium tree blocking the trail close to the church
-
- Orange - cleaned-up overgrown area close to Shoal Creek road
-
- Purple - removed two areas of small trees blocking a section of the upper trail
-
- Purple - cleaned up overgrown areas on upper trail
Leadership Meeting - 04/11 - Summary
-
Website stats indicate 400-500 people use the website each month
-
Puckett Bridge replacement
-
Location - replacement will be just upstream of current bridge.
-
Logistics - multiple work days likely to be needed. .
-
Rolling Barge - will most likely be using Rolling Barge modular bridge product. Continued discussion about bridge decking - pressure treated wood versus composite material versus something else
-
Networking - plans to reach out to SORBA with Allatoona Creek Trails. They previously built a Rolling Barge bridge at their mountain bike trails.
-
Funding - many people have previously have expressed interest in contributing to bridge replacement costs. Funds to be provided to Scouts Canton 501c3 for tax deductible donations.
-
Approval - Corps of Engineer approval will be needed. Full specs, location determination, and all details need to be ironed out prior to approaching the Corps.
-
-
4/27/2024 Work Day
-
Tree removal - will do recon to see if chainsaws will be needed
-
Weed eating - purple and yellow need weed eating, other trails likely will need attention to
-
Bridges - may need a small foot bridge on boggy section of Green
-
Blazing - need to complete re-blazing - Yellow and parts of White
-
-
Umbrella Insurance - policy needed to cover liability for leadership team
Work Day - 04/6/2024 - Blazing Trails
-
White: Church to Meadow (largely required new blazes because of the recent re-route)
-
White: Meadow to Jug Creek and back
-
Orange: Trailhead at White to Shoal Creek road and back
-
Green: Entire trail
-
Purple: Entire trail
Work Day - 02/21/2024
-
Trees removed from various trails
2023
Work Day - 12/08/2023
-
Repairs made to bridge W3 on the White trail. Over time, erosion and wet conditions resulted in considerable rot on end of the bridge. The bulk of the work was completed on 12/8, but final water diversion measures were completed in the following week.
Work Day - 12/08/2023
-
Repairs made to bridge W3 on the White trail. Over time, erosion and wet conditions resulted in considerable rot on end of the bridge. The bulk of the work was completed on 12/8, but final water diversion measures were completed in the following week.
Work Days - May 2023
-
Large oak on White in precarious location
-
Large, complex blowdown on Yellow